Document No. DER01120 Effective Date 25 May 07 Page No. 1 of 9 DESCRIPTION AND OPERATION DE-1000 CENTRIFUGE - GEARBOX DRIVE GENERAL The centr
bvacu-Flos Document No. DER12016 Effective Date 25 May 07 Page No. 1 of 1 SUPPLIER DATA DE-1000 CENTRIFUGE - GEARBOX DRIVE GENERAL This sect
Performance Data: M7064T-I Nameplate Data Rated Output 50 HP Volts 230/460 Full Load Amps 120/60 Speed 1775 Hertz 60 Phase 3 NEMA Design Code
Specifications: M7064T-I Catalog Number: M7064T-I Specification Number: 12S077X139H1 Horsepower: 50//40 Voltage: 230/460//190/380 Hertz: 60
Document No. DER01120 DESCRIPTION AND OPERATION Page 2 of 9 Effective Date 25 May 07 OPERATING PRINCIPALS (CONT’D) During centrifuge operation, sl
Boston Gear®ORC Series Trig-O-Matic™Overload Release Clutcheswww.bostongear.comDoc. No. ORC SeriesModel SInstallation and Maintenance Instructions
ORC SERIES, MODEL S CLUTCHES1ORC Series, Model SBOSTON GEARBOSTON GEAR®ORC SERIESTRIG-O-MATIC™OVERLOAD RELEASE CLUTCHES –STANDARD MODEL SINSTALLATION
ORC SERIES, MODEL S CLUTCHESORC Series, Model S2BOSTON GEARBOSTON GEAR®When an overload occurs, the rotor rotates from itsnormal position within the h
ORC SERIES, MODEL S CLUTCHES3ORC Series, Model SBOSTON GEARBOSTON GEAR®II. MOUNTING SPROCKETS OR SHEAVESTO CLUTCHA. Type T Housing (Refer to Figure 7)
ORC SERIES, MODEL S CLUTCHESORC Series, Model S4BOSTON GEARBOSTON GEAR®TABLE 4 - TYPE B HOUSING DIMENSIONSFSize A B C D E +.000 G-.0021 .81 .81 1.06 .
ORC SERIES, MODEL S CLUTCHES5ORC Series, Model SBOSTON GEARBOSTON GEAR®III. LOCATING AND MOUNTING CLUTCHAND COUPLINGS TO SHAFTA. LocationThe clutch sh
DESCRIPTION AND OPERATION Document No. DER01120 Effective Date 25 May 07 Page 3 of 9 MAJOR COMPONENTS Major components of the centrifuge (Figure 1
ORC SERIES, MODEL S CLUTCHESORC Series, Model S6BOSTON GEARBOSTON GEAR®5. Select the correct hex wrench from Table 5 andinsert it through the hole sta
Feeler GageORC SERIES, MODEL S CLUTCHES7ORC Series, Model SBOSTON GEARBOSTON GEAR®c. If a correction is required to satisfy angularalignment requireme
Limit Switch PinStandardLimitSwitchPinLimitSwitchStartJogStopTo MotorORCOverloadClutchLimit Switch Actuating MechanismLimitSwitchOptionalLimitSwitchAc
ORC SERIES, MODEL S CLUTCHES9ORC Series, Model SBOSTON GEARBOSTON GEAR®VI. REPAIR INSTRUCTIONSA. General Disassembly1. All item numbers in parenthesis
ORC SERIES, MODEL S CLUTCHESORC Series, Model S10BOSTON GEARBOSTON GEAR®4. Remove the drive pawl (10). The drive pawl and thedrive spring (18) will ha
ORC SERIES, MODEL S CLUTCHES11ORC Series, Model SBOSTON GEARBOSTON GEAR®D. Limit Switch Actuating Mechanism (LSAM)Assembly1. Apply a graphite lubrican
ORC SERIES, MODEL S CLUTCHESORC Series, Model S12BOSTON GEARBOSTON GEAR®157242625163101732425265614151920111213982718232221ORC SERIES, MODEL S WITH LI
ORC SERIES, MODEL S CLUTCHES13ORC Series, Model SBOSTON GEARBOSTON GEAR®Key No. Name Size 1 (Qty.) Size 2 (Qty.) Size 3 (Qty.) Size 4 (Qty.) Size 5 (Q
ORC SERIES, MODEL S CLUTCHESORC Series, Model S14BOSTON GEARBOSTON GEAR®342757112019151413745252662252612933414336831324036351841392829383243102322431
ORC SERIES, MODEL S CLUTCHES15ORC Series, Model SORC 2 SA C -LP16 - P16Series ModelType Torque Range Coupling Bore (Type C, N or R Only)Overload SA =
Document No. DER01120 DESCRIPTION AND OPERATION Page 4 of 9 Effective Date 25 May 07 Conveyor The conveyor assembly is a hollow, cylindrical auger
COUPLINGSBoston Gear14 Hayward StreetQuincy, MA 02171Tel 617.328.3300fax 617.479.6238www.bostongear.comCLUTCHESBoston Gear14 Hayward StreetQuincy, MA
®Revision Number: 1 Page 1 of 1Revision Date: 4-March-2004M:\cer\Derric
®Revision Number: 1 Page 1 of 1Revision Date: 4-March-2004M:\cer\Derric
®Revision Number: 1 Page 1 of 1Revision Date: 4-March-2004M:\cer\Derric
(J:\ENG\DOCS\Conformance\2\. . . Derrick®, Flo-Line®, FLC 2000™, Flo-Line Scalper™, Pyramid®, Sandwich Screens®, DE-1000™, Hi-G™, Vacu-Flo™, GBG™, PM
Document No. DER13000 Effective Date 15 Apr 05 Page No. 1 of ___ INSTALLATION AND MAINTENANCE LOG PURPOSE The ruled, blank pages provided w
Document No. DER13000 INSTALLATION & MAINTENANCE LOG Page ___ of ___ Effective Date 15 Apr 05 Notes:
INSTALLATION AND MAINTENANCE LOG Document No. DER13000 Effective Date 15 Apr 05 Page ___ of ___ Notes:
Document No. DER13000 INSTALLATION & MAINTENANCE LOG Page ___ of ___ Effective Date 15 Apr 05 Notes:
DESCRIPTION AND OPERATION Document No. DER01120 Effective Date 25 May 07 Page 5 of 9 Figure 1120-3 Overload Release Assembly FLUID COUPLING The
INSTALLATION AND MAINTENANCE LOG Document No. DER13000 Effective Date 15 Apr 05 Page ___ of ___ Notes:
Document No. DER13000 INSTALLATION & MAINTENANCE LOG Page ___ of ___ Effective Date 15 Apr 05 Notes:
Document No. DER01120 DESCRIPTION AND OPERATION Page 6 of 9 Effective Date 25 May 07 ELECTRICAL CONTROL BOX (CONT’D) Figure 1120-4 Electrical Con
DESCRIPTION AND OPERATION Document No. DER01120 Effective Date 25 May 07 Page 7 of 9 The vibration switch is mounted on the centrifuge frame in an
Document No. DER01120 DESCRIPTION AND OPERATION Page 8 of 9 Effective Date 25 May 07 ELECTRICAL CONTROL SYSTEM OPERATION The following paragraphs
DESCRIPTION AND OPERATION Document No. DER01120 Effective Date 25 May 07 Page 9 of 9 Vibration Tripping the vibration switch due to excessive vibr
HOW TO USE THIS “e-MANUAL” This electronic version of a Derrick Operating and Maintenance Manual has been prepared in Adobe® Acrobat® pdf format. Thi
Document No. DER01220 Effective Date 25 May 07 Page No. 1 of 1 EQUIPMENT SPECIFICATIONS DE-1000 CENTRIFUGE - GEARBOX DRIVE Equipment specif
Document No. DER01320 Effective Date 10 Oct 08 Supersedes 25 May 07 Page No. 1 of 1 SERVICES & UTILITIES REQUIRED DE-1000 CENTRIFUGE
Document No. DER01420 Effective Date 25 May 07 Page No. 1 of 3 EQUIPMENT HANDLING PROCEDURES DE-1000 CENTRIFUGE - GEARBOX DRIVE RECEIVING T
Document No. DER01420 EQUIPMENT HANDLING PROCEDURES Page 2 of 3 Effective Date 25 May 07 MOVING/POSITIONING THE EQUIPMENT (CONTINUED) Four reinfor
EQUIPMENT HANDLING PROCEDURES Document No. DER01420 Effective Date 25 May 07 Page 3 of 3 EQUIPMENT STORAGE General If equipment is not being instal
Document No. DER02020 Effective Date 25 May 08 Page No. 1 of 3 WARNINGS SUMMARY DE-1000 CENTRIFUGE - GEARBOX DRIVE GENERAL This section co
Document No. TOC00221 Effective Date 25 May 07 Page No. 1 of 2 TABLE OF CONTENTS DE-1000 CENTRIFUGE - GEARBOX DRIVE GENERAL INFORMATION...
Document No. DER02020 WARNINGS SUMMARY Page 2 of 3 Effective Date 25 May 08 EQUIPMENT HANDLING WARNING! USE SPREADER BARS TO PREVENT DAMAGE WHEN
WARNINGS SUMMARY Document No. DER02020 Effective Date 25 May 08 Page 3 of 3 MAINTENANCE WARNING! HIGH VOLTAGE MAY BE PRESENT. ALWAYS OPEN FUSED
Document No. DER02889 Effective Date 22 May 08 Supersedes 15 Jun 07 Page No. 1 of 1 MATERIAL SAFETY DATA SHEETS (MSDSs) DE-1000 CENTRIFUGE
Document No. DER02889 MATERIAL SAFETY DATA SHEETS (MSDSs) Page 2 of 2 Effective Date 22 May 08 Supersedes 15 Jun 07
MATERIAL SAFETY DATA SHEETThe information contained herein is based on data available at the time of preparation of this data sheet which ICI Paints b
Form: 359D, Page 2 of 3, prepared 05/06/08TOXICOLOGICAL INFORMATION (ANSI Section 11)Supplemental health information : Contains a chemical that is
Form: 359D, Page 3 of 3, prepared 05/06/08Chemical Hazard Data (ANSI Sections 2, 8, 11, and 15)ACGIH-TLV OSHA-PELS.R.Std.S2 S3 CCCommon Name CAS. No
MATERIAL SAFETY DATA SHEETThe information contained herein is based on data available at the time of preparation of this data sheet which ICI Paints b
Document No.TOC00221 TABLE OF CONTENTS Page 2 of 2 Effective Date 25 May 07 The content of this document is subjec
Form: 313K, Page 2 of 2, prepared 08/02/04Carcinogenicity : The international agency for research on cancer (IARC) has evaluated ethylbenzene and cl
Document No. DER03020 Effective Date 10 Oct 08 Supersedes 25 May 07 Page 1 of 7 INSTALLATION INSTRUCTIONS DE-1000 CENTRIFUGE - GEARBOX DR
Document No. DER03020 INSTALLATION INSTRUCTIONS Page 2 of 7 Effective Date 10 Oct 08 INSTALLATION SEQUENCE Following is the sequence of steps for i
INSTALLATION INSTRUCTIONS Document No. DER03020 Effective Date 10 Oct 08 Page 3 of 7 Figure 3020-1 Centrifuge Leveling SHIPPING COMPONENTS Note!
Document No. DER03020 INSTALLATION INSTRUCTIONS Page 4 of 7 Effective Date 10 Oct 08 SHIPPING COMPONENTS (CONT’D) Figure 3020-3 Shipping Componen
INSTALLATION INSTRUCTIONS Document No. DER03020 Effective Date 10 Oct 08 Page 5 of 7 FEED PUMP The customer must supply a positive-displacement fe
Document No. DER03020 INSTALLATION INSTRUCTIONS Page 6 of 7 Effective Date 10 Oct 08 ELECTRIC POWER CONNECTIONS (CONT’D) Figure 3020-5 Electric P
Document No. DER04097 Effective Date 27 Nov 07 Supersedes 25 May 07 Page No. 1 of 7 OPERATING INSTRUCTIONS DE-1000 CENTRIFUGE - GEARBOX D
Document No. DER04097 OPERATING INSTRUCTIONS Page 2 of 7 Effective Date 27 Nov 07 INITIAL STARTUP Perform the initial startup procedure when the ce
Document No. DER01019 Effective Date 25 May 07 Page No. 1 of 5 INTRODUCTION DE-1000 CENTRIFUGE - GEARBOX DRIVE OVERVIEW This manual provides
OPERATING INSTRUCTIONS Document No. DER04097 Effective Date 27 Nov 07 Page 3 of 7 OPERATION Monitor the liquid and solids discharges continually to
Document No. DER04097 OPERATING INSTRUCTIONS Page 4 of 7 Effective Date 27 Nov 07 Pond Depth Pond depth can only be adjusted with the centrifuge fu
OPERATING INSTRUCTIONS Document No. DER04097 Effective Date 27 Nov 07 Page 5 of 7 Bowl and Conveyor Speeds The faster the bowl speed, the faster so
Document No. DER04097 OPERATING INSTRUCTIONS Page 6 of 7 Effective Date 27 Nov 07 Overload Release Clutch Torque Frequent overload tripping that ca
OPERATING INSTRUCTIONS Document No. DER04097 Effective Date 27 Nov 07 Page 7 of 7 NORMAL SHUTDOWN The normal shutdown procedure is to be used for c
Document No. DER05017 Effective Date 25 May 07 Page No. 1 of 12 BEARING REPLACEMENT DE-1000 CENTRIFUGE GENERAL This procedure describes rep
Document No. DER05017 BEARING REPLACEMENT Page 2 of 12 Effective Date 25 May 07 Liquid End Pillow Block Bearing(Cont’d) 4. Remove Rotodiff / gea
BEARING REPLACEMENT Document No. DER05017 Effective Date 25 May 07 Page 3 of 12 5. Turn flange (Figure 5017-2) until large access holes in flange
Document No. DER05017 BEARING REPLACEMENT Page 4 of 12 Effective Date 25 May 07 Liquid End Pillow Block Bearing (Cont’d) Figure 5017-3 Liquid E
Document No. DER01019 INTRODUCTION Page 2 of 5 Effective Date 25 May 07 EQUIPMENT USE The DE-1000 GBD centrifuge is designed expressly to remove
BEARING REPLACEMENT Document No. DER05017 Effective Date 25 May 07 Page 5 of 12 Figure 5017-4 Liquid End Cross Section Solids End Pillow Block Be
Document No. DER05017 BEARING REPLACEMENT Page 6 of 12 Effective Date 25 May 07 Solids End Pillow Block Bearing (Cont’d) 5. Remove flathead scre
BEARING REPLACEMENT Document No. DER05017 Effective Date 25 May 07 Page 7 of 12 Cleaning, Inspection, and Repair 1. Clean all components with a s
Document No. DER05017 BEARING REPLACEMENT Page 8 of 12 Effective Date 25 May 07 Liquid End Pillow Block Bearing (Cont’d) 7. Slide assembled pill
BEARING REPLACEMENT Document No. DER05017 Effective Date 25 May 07 Page 9 of 12 5. Install new small cross-section O-ring against shoulder of inb
Document No. DER05017 BEARING REPLACEMENT Page 10 of 12 Effective Date 25 May 07 Solids End Pillow Block Bearing (Cont’d) 14. Apply a light coat
BEARING REPLACEMENT Document No. DER05017 Effective Date 25 May 07 Page 11 of 12 b. Remove retaining ring securing seal within seal housing. Remo
Document No. DER05017 BEARING REPLACEMENT Page 12 of 12 Effective Date 25 May 07 Installation (Cont’d) 2. To install the solids end conveyor bea
Document No. DER05018 Effective Date 15 Oct 07 Supersedes 25 May 07 Page No. Page 1 of 6 HARDWARE TORQUE SPECIFICATIONS DE-1000 CENTRIFUG
Document No. DER05018 HARDWARE TORQUE SPECIFICATIONS Page 2 of 6 Effective Date 15 Oct 07 Rotating Assembly Hardware Installation - Solids End
INTRODUCTION Document No. DER01019 Effective Date 25 May 07 Page 3 of 5 PRODUCT SUPPORT Derrick Corporation offers 24-hour per day, 7-day per week
HARDWARE TORQUE SPECIFICATIONS Document No. DER05018 Effective Date 15 Oct 07 Page 3 of 6 Solid End Hardware Installation No. Description Qty
Document No. DER05018 HARDWARE TORQUE SPECIFICATIONS Page 4 of 6 Effective Date 15 Oct 07 Rotating Assembly Hardware Installation- Liquid End
HARDWARE TORQUE SPECIFICATIONS Document No. DER05018 Effective Date 15 Oct 07 Page 5 of 6 Liquid End Hardware Installation No. Description Qt
Document No. DER05018 HARDWARE TORQUE SPECIFICATIONS Page 6 of 6 Effective Date 15 Oct 07 The content of this document
Document No. DER05022 Effective Date 25 May 07 Page No. 1 of 10 PREVENTIVE MAINTENANCE DE-1000 CENTRIFUGE - GEARBOX DRIVE GENERAL Preventiv
Document No. DER05022 PREVENTIVE MAINTENANCE Page 2 of 10 Effective Date 25 May 07 Figure 5022-1 Bearing Lubrication Points PARTS REPLACEMENT
PREVENTIVE MAINTENANCE Document No. DER05022 Effective Date 25 May 07 Page 3 of 10 MAINTENANCE PROCEDURES The following paragraphs describe mainte
Document No. DER05022 PREVENTIVE MAINTENANCE Page 4 of 10 Effective Date 25 May 07 Drive Belt (Cont’d) 6. Tighten motor mount adjustment bolts to
PREVENTIVE MAINTENANCE Document No. DER05022 Effective Date 25 May 07 Page 5 of 10 Figure 5022-3 Gearbox Removal 9. Note locations of all shims
Document No. DER05022 PREVENTIVE MAINTENANCE Page 6 of 10 Effective Date 25 May 07 Removal and Disassembly (Cont’d) b. Note locations of alignme
Document No. DER01019 INTRODUCTION Page 4 of 5 Effective Date 25 May 07 HIGHLIGHTED INFORMATION Information considered important to safe and eff
PREVENTIVE MAINTENANCE Document No. DER05022 Effective Date 25 May 07 Page 7 of 10 12. Remove conveyor assembly as follows: a. Remove four screws
Document No. DER05022 PREVENTIVE MAINTENANCE Page 8 of 10 Effective Date 25 May 07 Cleaning, Inspection, and Repair (Cont’d) 6. Inspect bowl inte
PREVENTIVE MAINTENANCE Document No. DER05022 Effective Date 25 May 07 Page 9 of 10 b. Insert six new hex head screws through gearbox flange and i
Document No. DER05022 PREVENTIVE MAINTENANCE Page 10 of 10 Effective Date 25 May 07 Reassembly and Installation (Cont’d) 14. After completing gear
Document No. DER05102 Effective Date 25 May 07 Page No. 1 of 2 TOOLS AND EQUIPMENT DE-1000 CENTRIFUGE GENERAL The following tool list inclu
Document No. DER05102 TOOLS AND EQUIPMENT Page 2 of 2 Effective Date 25 May 07 TABLE 5102-1 DE-1000 CENTRIFUGE TOOL LIST PART NO. DESCRIPTION /
Document No. DER05103 Effective Date 25 May 07 Page No. 1 of 5 TROUBLESHOOTING DE-1000 CENTRIFUGE - GEARBOX DRIVE GENERAL Although equipmen
Document No. DER05103 TROUBLESHOOTING Page 2 of 5 Effective Date 25 May 07 CHECK FOR CLOGGED CONVEYOR Troubleshooting should begin with determinin
TROUBLESHOOTING Document No. DER05103 Effective Date 25 May 07 Page 3 of 5 TROUBLESHOOTING CENTRIFUGE - FULL HYDRAULIC DRIVE Possible Cause Isolat
Document No. DER05103 TROUBLESHOOTING Page 4 of 5 Effective Date 25 May 07 TROUBLESHOOTING CENTRIFUGE - FULL HYDRAULIC DRIVE Possible Cause Isola
INTRODUCTION Document No. DER01019 Effective Date 25 May 07 Page 5 of 5 HOW TO USE THIS MANUAL DER XX 000 Subsection Number (000 thru 999) Sect
TROUBLESHOOTING Document No. DER05103 Effective Date 25 May 07 Page 5 of 5 The content of this document is subject to c
Document No. DER05104 Effective Date 25 May 07 Page No. Page 1 of 4 ADJUSTMENTS DE-1000 CENTRIFUGE - GEARBOX DRIVE GENERAL This section con
Document No. DER05104 ADJUSTMENTS Page 2 of 4 Effective Date 25 May 07 MOTOR SHEAVE REPLACEMENT (CONT’D) 12. Insert feed tube into feed tube suppor
ADJUSTMENTS Section No. DER05104 Effective Date 25 May 07 Page 3 of 4 c. Check that clutch has reset by attempting to rotate the cam/hub assembl
Document No. DER05104 ADJUSTMENTS Page 4 of 4 Effective Date 25 May 07 Overload Release Clutch Torque (Cont’d) Figure 5014-3 Setting Overload Rel