HP Storage Essentials SRM 6.0 User Guide 223
NOTE: If you are using the prstat utility, all of the processes will be named java.exe.
Editing a Collector Schedule
There are several ways to modify a collector schedule:
Locate the collector you want to edit in the collector table, and click the Edit ( ) button in that
collector’s row.
Locate the collector you want to edit in the collector table, and select the collector using the
checkbox in the first column of the table. You can select one or more collectors this way. Click
the Edit Selected button above the collector table to modify the selected collector’s schedules at
the same time.
If you want to modify all of the collectors displayed on the same page of the collector table, click
the checkbox in the first column header, and then click the Edit Selected button above the table.
If you want to modify all of the collectors displayed on all of the pages, click the Select All Pages
link above the collector table, and then click the Edit Selected button above the table.
When you edit a collector schedule, you can change the following schedule properties:
Next Scheduled Run – Specifies a start time for when the collector should run.
Repeat Interval – Specifies how often the collector should run on a recurring basis.
Spread Start Time – This checkbox can only be selected when more than one collector is being
edited. If you select this checkbox, the management server automatically adjusts the start time of
the selected collectors and spreads the load of the collectors across the specified repeat interval.