2-19
Installing the Switch
Installation Procedures
Figure 2-16. Installing Hold-down and Mounting Brackets on a 6600 Switch:
Option 3 - Port-Side Mounting
4. Install M6 cage nuts (shipped in the rack mount kit) in the appropriate
post holes for the switch you are installing. Then slide the switch into the
rails until the switch is fully inserted and the mounting hole in each
bracket lines up with the cage nut in each rack post.
• If you are installing a 6600 Switch with the port side facing the cold
aisle, no air plenum is necessary.
i. Install two M6 cage nuts in the appropriate post holes. Then slide
the switch into the rack and secure it using two M6 screws (one
screw and cage nut per bracket).
ii. Connect each power cord to the switch and secure it with a velcro
strap. Then route each cord through the rack.
Figure 2-17. Installing a 6600 Switch in a Port-Side HP 10000 Series Mounting
No air plenum is used in a port-side mounting.
Install each mounting bracket with four M4 screws so that the end
of the mounting bracket is flush with the front panel of the 6600
Switch.
Option 3 - Port-side mounting for all 6600 Switches
Install each hold-down bracket with two M4 screws at the back
of the switch. Ensure that the end of the bracket is flush with the
end of the switch and does not hang over.
Install and tighten an M6 screw in each mounting bracket to
secure the 6600 Switch.
In a port-side-front mounting, slide the 6600 Switch into the rails.